Fixed-Price vs. Cost-Plus Contracts: What Homeowners Need to Know

By [Founder Name] · April 11, 2026 · 5 min read

Every building contract falls into one of two broad categories, and the difference between them determines who absorbs the risk if something costs more than expected.

Fixed-price contracts

The builder quotes one total price for the agreed scope of work, based on their own cost estimates and margin. If material or labour costs rise during the build, that's the builder's risk to absorb, not yours — provided the scope doesn't change.

Cost-plus contracts

The homeowner pays the actual cost of materials and labour, plus an agreed builder's fee (a fixed amount or percentage). If costs rise, the homeowner pays the difference — the builder's risk is much lower, and so, in theory, is their margin.

Why this matters more than the headline price

A cost-plus quote can look lower upfront precisely because it isn't carrying any contingency for risk — that risk hasn't disappeared, it's just moved to you. A fixed-price quote that looks a little higher is often pricing in exactly the protection a cost-plus contract doesn't offer.

Every project we build runs on a fixed-price contract, agreed before construction starts — see our guarantee for exactly what that covers. If you're comparing quotes from different builders, ask which type of contract each one is offering; it's often more revealing than the number itself.